Project update: June 25, 2018

As Castle Rock Water continues to ensure a strong water future, plans are underway for new groundwater wells. Castle Rock Water is building a new municipal well facility and pipeline at the corner of Lantern Circle and Lost Canyon Ranch Road, east of Matney Park. These wells will enhance our water service and provide high-quality drinking water to our residents.

Project details


Well drilling


Last summer, one of the two wells was drilled. Drilling of the second well began in mid-February and continues. Some unforeseen situations have occurred, and the drilling is expected to take longer than originally scheduled. Once the well is finished, connection to the main pipe and some electrical work will be completed. Construction is expected to wrap up in fall 2018.

Well house construction


Construction of the well house to enclose the wells is expected to be completed in summer 2018. Construction will occur during daytime hours (7 a.m.-6 p.m.).

Pipeline construction 

 
A pipeline to connect the wells to Founders Water Treatment Plant is being constructed along the power line corridor between Lantern Circle and High Plains Place. The new pipeline is represented in blue on the map and will tie into the existing (purple) infrastructure. Expect construction equipment along all sections of the (blue) pipeline.


  • At the Disc Golf Course the baskets for holes 3, 4, 5, and 7 are located in the construction area. Hole No. 3 is currently closed. Holes 1 and 2 should be usable. Holes 6 and 8 should be playable, but the tee boxes will be located in the construction zone, and players will need to start outside the construction area. The tee boxes at those holes will be reconstructed once construction is complete. Holes 2 and 3 may eventually need to be relocated due to the location of the well facility.
  • A small section of the Mitchel Creek Trail underneath the power lines will be closed between East Manchester Drive and Mikelson Boulevard. (Designated in red on the map.) A rudimentary detour (yellow) will be provided. This detour may not be handicap accessible. However, all unaffected and accessible trails in the area are designated in green. 
  • Several trail access points along the paved trail underneath the power lines have been closed during construction in order to ensure users' safety.
  • No roads will be closed. The pipeline will go under the roads through an existing line; thus, no road closures are scheduled. However, some sidewalks may be closed during construction.
Completion for the entire project, including site and trail restoration and revegetation, is scheduled for summer 2018.
  • At the Disc Golf Course the baskets for holes 3, 4, 5, and 7 are located in the construction area. Hole No. 3 is currently closed. Holes 1 and 2 should be usable. Holes 6 and 8 should be playable, but the tee boxes will be located in the construction zone, and players will need to start outside the construction area. The tee boxes at those holes will be reconstructed once construction is complete. Holes 2 and 3 may eventually need to be relocated due to the location of the well facility.
  • A small section of the Mitchel Creek Trail underneath the power lines will be closed between East Manchester Drive and Mikelson Boulevard. (Designated in red on the map.) A rudimentary detour (yellow) will be provided. This detour may not be handicap accessible. However, all unaffected and accessible trails in the area are designated in green. 
  • Several trail access points along the paved trail underneath the power lines have been closed during construction in order to ensure users' safety.
  • No roads will be closed. The pipeline will go under the roads through an existing line; thus, no road closures are scheduled. However, some sidewalks may be closed during construction.
Completion for the entire project, including site and trail restoration and revegetation, is scheduled for summer 2018.
  • At the Disc Golf Course the baskets for holes 3, 4, 5, and 7 are located in the construction area. Hole No. 3 is currently closed. Holes 1 and 2 should be usable. Holes 6 and 8 should be playable, but the tee boxes will be located in the construction zone, and players will need to start outside the construction area. The tee boxes at those holes will be reconstructed once construction is complete. Holes 2 and 3 may eventually need to be relocated due to the location of the well facility.
  • A small section of the Mitchel Creek Trail underneath the power lines will be closed between East Manchester Drive and Mikelson Boulevard. (Designated in red on the map.) A rudimentary detour (yellow) will be provided. This detour may not be handicap accessible. However, all unaffected and accessible trails in the area are designated in green. 
  • Several trail access points along the paved trail underneath the power lines have been closed during construction in order to ensure users' safety.
  • No roads will be closed. The pipeline will go under the roads through an existing line; thus, no road closures are scheduled. However, some sidewalks may be closed during construction.
Completion for the entire project, including site and trail restoration and revegetation, is scheduled for summer 2018.
  • At the Disc Golf Course the baskets for holes 3, 4, 5, and 7 are located in the construction area. Hole No. 3 is currently closed. Holes 1 and 2 should be usable. Holes 6 and 8 should be playable, but the tee boxes will be located in the construction zone, and players will need to start outside the construction area. The tee boxes at those holes will be reconstructed once construction is complete. Holes 2 and 3 may eventually need to be relocated due to the location of the well facility.
  • A small section of the Mitchel Creek Trail underneath the power lines will be closed between East Manchester Drive and Mikelson Boulevard. (Designated in red on the map.) A rudimentary detour (yellow) will be provided. This detour may not be handicap accessible. However, all unaffected and accessible trails in the area are designated in green. 
  • Several trail access points along the paved trail underneath the power lines have been closed during construction in order to ensure users' safety.
  • No roads will be closed. The pipeline will go under the roads through an existing line; thus, no road closures are scheduled. However, some sidewalks may be closed during construction.
Completion for the entire project, including site and trail restoration and revegetation, is scheduled for summer 2018.
Castlewood Ranch 1 Well Facility Map

Closures and affected areas 


  • At the Disc Golf Course, the baskets for holes 3, 4, 5, and 7 are located in the construction area. Hole No. 3 is currently closed. Holes 1 and 2 should be usable. Holes 6 and 8 should be playable, but the tee boxes are in the construction zone, and players need to start outside the construction area. The tee boxes at those holes will be reconstructed once construction is complete. Holes 2 and 3 may eventually need to be relocated due to the location of the well facility.
  • A small section of the Mitchel Creek Trail underneath the power lines will be closed between East Manchester Drive and Mikelson Boulevard. (Designated in red on the map.) A rudimentary detour (yellow) will be provided. This detour may not be handicap accessible. However, all unaffected and accessible trails in the area are designated in green.  
  • Several trail access points along the paved trail underneath the power lines have been closed during construction in order to ensure the the safety of trail users.
  • No roads will be closed. The pipeline will go under the roads, through an existing line; thus, no road closures are scheduled. However, some sidewalks may be closed during construction.
Completion for the entire project, including site and trail restoration and revegetation is scheduled for summer 2018.